Which document confirms acceptance testing by the FDNY in NYC after a system is installed?

Prepare for the FDNY COF S-98 Exam. Study with flashcards and multiple choice questions, each question has hints and explanations. Excel on your exam!

Multiple Choice

Which document confirms acceptance testing by the FDNY in NYC after a system is installed?

Explanation:
The key idea is knowing which document officially proves the fire alarm system has been tested and accepted by FDNY after installation. The formal record is the FDNY acceptance test certificate or approval document. It shows the system was tested to meet NYC code requirements and was found satisfactory by FDNY or an authorized entity under FDNY oversight, and it provides official proof for the building files and authorities. Internal notes aren’t official records of testing, a contractor’s invoice is financial, and a building occupancy permit indicates the building can be occupied but does not document the FDNY acceptance testing of the fire alarm system.

The key idea is knowing which document officially proves the fire alarm system has been tested and accepted by FDNY after installation. The formal record is the FDNY acceptance test certificate or approval document. It shows the system was tested to meet NYC code requirements and was found satisfactory by FDNY or an authorized entity under FDNY oversight, and it provides official proof for the building files and authorities.

Internal notes aren’t official records of testing, a contractor’s invoice is financial, and a building occupancy permit indicates the building can be occupied but does not document the FDNY acceptance testing of the fire alarm system.